Hi Friends,
I am using 'Automatic reorder point' (V2) planning. It works well but one hitch is there.
If the calculated reorder point in 1.33, SAP is rounding it down to 1 (UoM is EA). for anything above 1.5, it is being round correctly to 2.
But I want the reorder point to be always rounded up (so 1.33 should be 2).
I have maintained the parameter MM_FCST_ROUND = ' ' (Blank) as suggested by OSS notes. But that is not helping me in this problem. May be it rounds the forecast but not the reorder point?
Am I missing something here?